Forsmark F1, F2, F3 BWR / Sweden
  • Project began 1996
  • Installed complete process surveillance system
  • Within containment there are 45 RADCAM delivery starting 2009
  • Throughout the facility there are over 150 other analogue and IP cameras
  • IVS3000 advanced video matrices installed in each reactor
  • IVS AVISS installed in each reactor (AVISS is the nuclear version of the IVS-MCP)
  • IVS-AVR installed in each reactor
  • IVS-Server installed within each reactor
  • Complete delivery of parts and documentation was on schedule
Oskarshamn OKG3 BWR / Sweden
  • Project began 2009
  • Start 2009, tested 3 RADCAM in containment for 30 months in 2 units
  • 2011 Purchased 16 RADCAM cameras
  • 2012 Integrated all cameras into existing control system with existing cabling with assistance from ISEC, system commissioned
  • Complete system and documentation delivered  on schedule
Oskarshamn OKG2 BWR / Sweden
  • Project began 2013
  • Start 2013, tested 1 RADCAM in containment for 12 months
  • 2014 Purchased 8 RADCAM cameras
  • 2014 Will integrate all cameras into existing control system with existing cabling with assistance from ISEC
  • Complete system and documentation delivered  on schedule
Fukushima TEPCO BWR / Japan
  • Project began 2011
  • Delivered 12 RADCAM cameras to aid in recovery effort
  • Cameras currently in use under “clean up tent” in high gamma area
  • 2012 TEPCO placed order for five additional units
  • Delivered on schedule
EDF France (Multiple PWR Sites)
  • Project began 1998
  • Provided complete outer security IVS3000 systems for 5 nuclear power plants
  • 2011 Provided 6 RADCAM cameras to 4 nuclear power plants
  • 2012 ISEC selected to provide RADCAM  cameras for project “VD3” 1300MW plant upgrades (22 reactors total)
  • 2012 ISEC selected to provide RADCAM  cameras for project “ VD4 900MW” plant upgrades (28 reactors total)
  • Delivered equipment and documentation on schedule
Leibstadt BWR / Switzerland
  • Project began 2012
  • Delivered a surveillance system for Drywell area
  • Project consisted of 3 RADCAM cameras
  • Integration to Seetek VMS system
  • Delivered equipment and documentation on schedule
  • 2013 delivered 1 RADCAM and 1 RADCAM Omega
SKB CLAB (Nuclear Fuel & Waste Management) / Sweden
  • Project began 2010
  • Delivered security video surveillance system integrated into alarm management system
  • Project included  IVS-AVR, IVS-MCP, and  IVS-Server
  • Delivered equipment and documentation on schedule
Brunnswick BWR / USA
  • Project began 2013
  • 1 test camera RADCAM installed and running since April -13 in Drywell, connected to encoder and 3-third party VMS-system
  • 38 RADCAM Omegas delivered for turbine halls
  • Delivered equipment and documentation on schedule
Ringhals R1, R2, R3, R4 BWR & 3x PWR / Sweden
  • Project began 2013
  • Installing complete process surveillance system
  • Within containment there are 65 RADCAM delivery starting March 2013
  • IVS3000 advanced video matrices installed in each reactor
  • IVS AVISS to be installed in each reactor (AVISS is the nuclear version of the IVS-MCP)
  • IVS-AVR to be installed in each reactor
  • IVS-Server to be installed within each reactor
Loviisa VVER / Finland
  • Project began 2013
  • Delivered standalone RADCAM system for initial test in VVER reactor
  • Complete delivery of parts and documentation was on schedule
Harris PWR / USA
  • Project began 2013
  • Delivered 1 RADCAM to be installed during next outage period
  • Complete delivery of parts and documentation was on schedule
Robinson NPP PWR / USA
  • Project began 2013
  • Delivered 1 RADCAM for use during next outage – Aug. 2013
  • Complete delivery of parts and documentation was on schedule
Thiange PWR / Belgium
Beznau PWR / Switzerland
  • Project began 2012
  • Delivered 1 RADCAM to be installed during next outage
  • Complete delivery of parts and documentation was on schedule
Grand Gulf NPP BWR / USA
  • Project began 2013
  • Delivered 1 RADCAM for use during next outage – Aug. 2013
  • Complete delivery of parts and documentation was on schedule
McGuire NPP PWR / USA
  • Project began 2013
  • Delivered 2 RADCAMS for use during next outage – Aug. 2013
  • Complete delivery of parts and documentation was on schedule
Salem NPP PWR / USA
  • Project began 2014
  • Delivered 8 RADCAMS for use during next outage – April. 2014
  • Complete delivery of parts and documentation was on schedule
Wolf CREEK NPP PWR / USA
  • Project began 2014
  • Delivered 1 RADCAMS for use during next outage
  • Complete delivery of parts and documentation was on schedule
Nine Mile Point NPP BWR / USA
  • Project began 2014
  • Delivered 36 RADCAMS for installation beginning next outage 2015
  • Complete delivery of parts and documentation was on schedule
CALVERT CLIFFS NPP PWR / USA
  • Project began 2014
  • Delivered 15 RADCAMS for installation beginning next outage 2015
  • Complete delivery of parts and documentation was on schedule
Leibstadt BWR / Switzerland
  • Project began 2014
  • Delivering a custom surveillance/documentation system for spent resin waste
  • Project consists of 9 RADCAM cameras and custom software documentation system to allow for tracking and archival of all casks within the plant
  • Integration to ISCE VMS system and documentation archival system
  • Equipment scheduled to be delivered April 2015 on schedule
Nine Mile Point NPP BWR / USA
  • Project began 2015
  • Delivered 4 RADCAM OMEGAS for the monitoring of radwaste
  • Complete delivery of parts and documentation was on schedule
Beznau PWR / Switzerland
  • Project began 2015
  • Delivered 2 RADCAMS and complete VMS system to be installed during next outage
  • Complete delivery of parts and documentation was on schedule
TURKEY POINT PWR / USA
  • Project began 2015
  • Delivered 1 RADCAM to be installed during next outage
  • Complete delivery of parts and documentation was on schedule
Leibstadt BWR / Switzerland
  • Project began 2015
  • Delivered 4 RADCAMS for steam tunnel to be installed during next outage
  • Complete delivery of parts and documentation was on schedule
River Bend BWR / USA
  • Project began 2015
  • Delivered 2 RADCAMS for steam tunnel to be installed during next outage
  • Complete delivery of parts and documentation was on schedule
Krsko NPP / Slovenia
  • Project began 2016
  • Delivered 6 RADCAMS and AVISS VMS system
  • Complete delivery of parts and documentation was on schedule
  • Installed successful
Fitzpatrick BWR / USA
  • Project began 2017
  • Delivered 4 RADCAMS for Drywell and 4 Omegas to be installed during next outage
  • Complete delivery of parts and documentation was on schedule
Surry PWR / USA
  • Project began 2018
  • Delivered 1 RADCAM for test to be installed within Bio Shield
  • Complete delivery of parts and documentation was on schedule